Printer capacity planner

Estimate expected saleable output from available printer time, utilization, batch size and full-batch failures.

hours
%
hours
items
%

Method: distinguish available time from output

Scheduled hours = available hours × utilization fraction.
Expected successful batches = scheduled hours ÷ batch hours × (1 − failure fraction).
Expected saleable items = floor(expected successful batches × items/batch).

Utilization covers idle time, setup gaps and other time you cannot schedule as printing. Failure covers the loss of scheduled attempts. Do not include the same downtime in both inputs. Use total printer-hours across comparable machines only if batch time and success assumptions are representative.

Worked example: 120 available hours

At 80% utilization, 96 hours are scheduled. Four-hour batches allow 24 attempts over a continuous planning horizon. At 10% total failures, the expectation is 21.6 successful batches. Six items per success gives 129.6 expected items, shown as 129 after rounding down. Fractional batches express a long-run average; they are not completed plates.

For a delivery promise, build an actual schedule

A period-end cutoff can leave an unfinished batch, and the continuous average model does not account for that boundary. It also does not schedule cooling, material changes, weekends or a person’s finishing queue. Use conservative inputs and a real calendar before promising a customer quantity or deadline. Expected output is not guaranteed output.

Test the other bottlenecks

If 129 items each need ten minutes of finishing, that is 21.5 hands-on hours before packing. A printer fleet may have spare capacity while labour is fully booked. Compare the output with break-even units, actual demand and the finishing time recorded for each product.

Inputs are not saved between visits. Export the current result before closing the page. Read the methodology and privacy information.