Calculation methodology
Every formula, assumption and limitation behind the 3D PrintMargin pricing calculator.
The pricing calculator models one repeatable batch of identical saleable items. Enter all amounts in one currency. The currency selector formats the output; it does not convert money. Calculations use unrounded values internally and display money to two decimal places.
| Symbol / input | Meaning |
|---|---|
| w, s, g | Batch filament grams, spool price, spool grams |
| t, W, e, a | Batch hours, average watts, price/kWh, machine allowance/hour |
| q, r | Whole saleable items per successful batch, failed-batch fraction |
| l, h, k | Hands-on minutes/batch, labour rate/hour, fulfilment cost/item |
| f, b, m | Percentage selling-fee fraction, fixed fee/item, target margin fraction |
From production cost to selling price
- Material M = w × (1 + waste% ÷ 100) × s ÷ g.
- Electricity E = W ÷ 1,000 × t × e. Machine allowance A = t × a.
- Expected production per successful batch B = (M + E + A) ÷ (1 − r).
- Failure reserve = B − (M + E + A).
- Cost per item C = (B + l ÷ 60 × h) ÷ q + k.
- Required price P = (C + b) ÷ (1 − f − m).
- Selling fees = P × f + b. Profit/item = P − C − fees.
- Profit per printer-hour = profit/item × q ÷ [t ÷ (1 − r)].
The fee and margin denominator follows from P − C − (fP + b) = mP. It is not a markup added to cost. Fees plus margin must be below 100%. The calculated price is an estimate, not a market valuation.
Reproduce the default example
| Step | Default input or result |
|---|---|
| Material | 120 g × 1.10 × $25 ÷ 1,000 g = $3.30 |
| Power and machine | 0.120 kW × 6 h × $0.18 = $0.1296; 6 h × $0.25 = $1.50 |
| Failure adjustment | ($3.30 + $0.1296 + $1.50) ÷ 0.90 = $5.477333… |
| Labour and fulfilment | 15 ÷ 60 × $20 = $5/batch; $0.75/item |
| Cost per item | ($5.477333… + $5) ÷ 4 + $0.75 = $3.369333… |
| Price | ($3.369333… + $0.30) ÷ (1 − 0.10 − 0.30) = $6.115555… |
| Profit and throughput | $1.834666…/item; $1.1008 per expected printer-hour |
The display rounds price to $6.12. Quoting exactly $6.12 produces a slightly different margin than the unrounded model. Batch revenue is calculated from the unrounded price, so displayed per-item prices multiplied by quantity can differ by a few cents.
Assumptions that can change your answer
A failed attempt is assumed to use the entire batch’s material, power and machine time and produce no saleable items. At 10% failures the expected attempts per success are 1 ÷ 0.90 = 1.1111, not 1.10. Early failures can cost less, while partial failures do not match an all-or-nothing batch. Use records to decide whether this reserve is appropriate.
Labour is added once per successful batch. Include expected restart and cleanup work in the labour input. Packaging and the fixed fee are per item, not per order; split an order-level fee across its items yourself. For mixed products, calculate separate cost groups instead of treating unequal items as identical.
What is excluded
Automatic tax calculations, tax registration thresholds, live exchange rates, live marketplace fees, unsold inventory, refunds, design licences, rent and marketing are not automatically added. Include seller-paid shipping in fulfilment if it is not charged separately. Sales tax collected for remittance is not profit. The machine-hour allowance should recover the expenses you assign to it without also adding those same costs elsewhere.
Choose inputs you can defend
Use slicer totals including supports and purge, a plug-in meter for average electricity use, a timer for active labour, and recent comparable batches for failures. Record the observation period. Changing material, nozzle, plate packing or finishing can invalidate an old average. Recheck actual cost after an order before adopting the quote as a permanent price.
Companion tool boundaries
The business tools use simplified contribution, capacity and payback models with formulas shown on each page. Do not add monthly overhead to both variable unit cost and fixed overhead. A positive calculation does not establish demand or guarantee that capacity will sell.
Reproduce the example in the pricing calculator · Compare three worked pricing scenarios
Workshop tools — model 1.2
Batch comparison uses supplied production totals and expected occupied time, with no second failure reserve. Resin pricing applies a full-failure reserve to printing inputs, then adds wash/cure, consumables and expected labour. Electricity measurement derives energy from the difference between meter readings. Actual-cost tracking uses observed totals without adding an estimated reserve. Quote totals use cent-rounded line amounts and a user-specified tax rate. Each page shows its formula and boundaries.